Showing posts with label Vista Francisco Pump Station. Show all posts
Showing posts with label Vista Francisco Pump Station. Show all posts

Friday, January 8, 2010

Crews almost two months ahead of schedule!


Crews working on the new Vista Francisco Pump Station have progressed rapidly and are almost two months ahead of schedule, which bodes well for an early completion date.

Wednesday, November 18, 2009

Construction Update


Construction on the new Vista Francisco Pump Station building located on Crestline Drive is progressing on schedule. Crews have begun the pouring of concrete for the foundation of the new water pumping station building.