Friday, November 6, 2009

Street Restoration Updates


Street restoration on Sanchez Street from Market to about 200 feet south of Duboce has been rescheduled to start on Monday, November 23 and will last no more than 3 days.


To expedite the completion of this project, weekend work is scheduled for Nov. 14, & 15, and Nov. 21 & 22. Construction activity will take place on the north side of Duboce near Sanchez St. We will provide information on weekend construction hours next week.

4 comments:

  1. The update is now not clear. It says work will start Nov. 23rd. Does that mean the weekend work that is starting as early as Nov. 14th is still going on as planned??

    ReplyDelete
  2. Sorry for the confusion. There are two different construction locations on different dates.

    1) Monday, November 23: Street restoration on Sanchez from Market to about 200 feet south of Duboce is scheduled to start;
    2) The weekend work that is limited to north of Duboce street at the intersection of Sanchez will begin this weekend.

    ReplyDelete
  3. Only half of the Sanchez Street Restoration between Market and Duboce is done. Some construction equipment remains (abandoned?) in a much-needed parking space at Sanchez/14th Street.

    When will the rest of the work be done?

    ReplyDelete
  4. Thanks for your comment Niel. Our restoration work on that portion of Sanchez Street is scheduled to be completed sometime in the next 2 weeks.  The piece of equipment at the corner of 14th and Sanchez will be removed today, Tuesday 12/1.

    ReplyDelete