Wednesday, November 25, 2009

Main Break on Waller and Steiner Repaired

Vibrations from road paving in the middle intersection of Waller and Steiner caused an old 2" air valve to break from an existing 16" water pipe around 1:20 pm Wednesday, Nov. 25. Our water operations crew responded immediately and the repair was done by 2:30 pm.

Crew will continue street restoration at the intersection of Waller and Steiner and is expected to be completed today.

Thursday, November 19, 2009

Happy Thanksgiving!


Construction will continue on the north side of Duboce Street at the intersections of Sanchez and Steiner this Sat. 11/21 and Sun. 11/22. Work hour 8:00 am to 8:00 pm (see last posting for detail information).


There will be no work on Thur. 11/26 and Fri. 11/27. We wish you a
Happy Thanksgiving!!

Wednesday, November 18, 2009

Construction Update


Construction on the new Vista Francisco Pump Station building located on Crestline Drive is progressing on schedule. Crews have begun the pouring of concrete for the foundation of the new water pumping station building.

Tuesday, November 10, 2009

Weekend Work

Weekend Work Scheduled for
Sat & Sun 11/14 – 11/15 and
Sat & Sun 11/21 – 11/22


What: The SFPUC is working to expedite the completion of the Noe Valley Transmission Main Replacement Project and has scheduled work on the weekends noted above. Work will begin on the north side of Duboce Street at the intersections of Sanchez and Steiner.

Work Hours: Construction starts at 8:00 am to 8:00 pm and may extend if necessary.

Traffic: One lane of traffic will remain open and a traffic control will be onsite to direct traffic.

Muni N Judah line: Please check with Muni for update as the schedule for the line will be impacted and allow additional travel time.

Construction Noise: Contractor will make efforts to minimize construction noise.

Parking: Parking will be restricted near the intersections. Please plan your parking accordingly.

Friday, November 6, 2009

Street Restoration Updates


Street restoration on Sanchez Street from Market to about 200 feet south of Duboce has been rescheduled to start on Monday, November 23 and will last no more than 3 days.


To expedite the completion of this project, weekend work is scheduled for Nov. 14, & 15, and Nov. 21 & 22. Construction activity will take place on the north side of Duboce near Sanchez St. We will provide information on weekend construction hours next week.

Friday, October 30, 2009

Construction Update


Contractor will finish up work at the southeast intersection of Sanchez and Duboce (directly across from the Duboce Park Café) next week and begin to remove construction equipment from Sanchez Street south of Duboce. Final street paving on Sanchez Street from Market to about 200 feet south of Duboce is scheduled to start on November 9.

To expedite this project weekend work has been scheduled for Nov. 14, & 15, and Nov. 21 &22. Construction activity will take place on the north side of Duboce near Sanchez St.. We will provide updates on the schedule of weekend construction activity.

Friday, October 23, 2009

WATER SERVICE INTERRUPTION

Tues, Oct 27, 2 AM – 6 AM
Location:

· 15th St. from Noe to Sanchez
· Henry St. from Noe to Sanchez
· Noe St. from 14th to 16th
· Market St. from Sanchez to Noe

Wed, Oct 28, 2 AM – 6 AM
Location:

· 14th St. from Noe to Church
· 166 Sanchez St.
· Belcher St. from 14th to Duboce

Emergency: 550-4956

SFPUC water operations will be connecting the new water main to the city water system. This will require temporary interruption of your water service during the dates and hours listed above. We apologize in advance for this inconvenience.

This activity is being conducted overnight to minimize disruption to businesses in the area.
If you have any specific health or water needs, please contact us immediately 554-3244. We will coordinate between our water operations crews and our Public Health department representative.

Construction noise can be expected for residents who live near Sanchez at 15th and Sanchez at Henry Streets on 10/27 and Sanchez at 14th and 166 Sanchez on 10/28. We have instructed the crews to minimize disruption.

Following the shut-down, we recommend running your tap for a few minutes and save the water for your plants. Visit sfwater.org/district 8 for updates.