Construction Update - Duboce Triangle and Lower Haight


Steiner from Duboce to Haight
Crew will begin installing 24-inch transmission main on Steiner from Duboce to Waller as soon as next week and then continue on Steiner from Waller to Haight. This phase of the work is expected to complete in 3 weeks. During construction, one lane of traffic will remain open for both cars and bikes. We have worked with the Department of Parking and Traffic on alternative routes and encourage bikers to use alternatives to avoid accidents.

Sanchez from Market to Duboce
City water operations crew will start working on pressure testing and making service connections to home and businesses. Traffic will be detoured. Please allow additional time for traffic. This phase of work is expected to be completed in 3 weeks.

Work Hours: 8:00 am - 5:00 pm
Parking: We will make every efforts to minimize parking impact. If you don’t see construction by noon, you are allowed to park. Duration:The project is anticipated to complete before Thanksgiving holiday.

Thanks you for patience and cooperation.