Thursday, May 21, 2009

Excavation begins at Sanchez & Market


Crew will begin excavation work at the intersection of Sanchez and Market streets early next week and Sanchez and 17th streets the following week installing new 8 and 24-inch water transmission mains. This work involves digging of large pits on both sides of the intersection and then pushing pipe through the pits. Duration: 8 weeks

Sidewalks will remain open, but PG&E may need to close sections of the sidewalk at 17th and Sanchez streets and Market and Sanchez streets for utility work.

Construction crews will continue working at the following locations in the next few weeks:

19th Street between Sanchez and Noe. Duration: 3 weeks

Sanchez between 16th to 18th streets: Duration: 4 weeks

We might need to come back to the same streets to continue work. We appreciate your patience as we work to improve your drinking water delivery system. For updates and comments on the project, please visit: sfwater.org/district8

Friday, May 8, 2009

Weekend work at the intersection of Sanchez and Market streets; Sanchez and 18th streets

Crew will be working at the intersection of Sanchez and Market streets this weekend, May 9 and May 10, and on Sanchez and 18th streets next weekend, May 16 and May 17 installing 8- and 24-inch water transmission mains. This weekend work is necessary because it’s the only time MUNI can take buses off-line so that construction work can proceed.

Construction crews will continue working at the following locations in the next few weeks:

19th Street between Sanchez and Noe. Duration: 3 weeks

Sanchez and Market Streets. Duration: 8 weeks

Tunneling and new water main installation will take place at the intersection of Sanchez and Market streets for 8 weeks.

Sidewalks will remain open, but PG&E and Comcast may need to close sections of the sidewalk at 17th and Sanchez streets and Market and Sanchez streets for utility work.

Thursday, April 16, 2009

Construction Updates # 5



Construction crews will be working at the following locations installing an 8 and 24-inch water transmission main late this week or early next week:

 Noe Street between 19th and 20th. Duration: 7 days
 19th Street between Sanchez and Noe. Duration: 10 days
 Intersection of Sanchez and 18th Streets. Duration: 3 days.
 Sanchez between 17th and 18th Streets. Duration: 7 days
 Sanchez between 16th and 17th Streets. Duration: 10 days.

Traffic: One-lane traffic will be maintained. Flag persons will be on site to direct traffic. Work Hours: 8:00 am – 5:00 pm.

Parking: Restricted parking signs have been posted. If no construction takes place by noon, public parking is permitted. The areas currently used to lay down transmission pipes will be occupied for approximately 5 weeks.

Sidewalks will remain open, but PG &E may need to close sections of the sidewalk at 17th and Sanchez Streets for utility work.

We appreciate your patience as work to improve your drinking water delivery system.

Wednesday, April 8, 2009

Construction at Noe btw 20th & Liberty and Sanchez btw 17th & 18th

Crew currently working at Noe Street between 22nd and 21th Streets will proceed to the following locations later this week:

1) Noe Street between 20th and Liberty Streets for a 24-inch water transmission main installation. Sidewalks will remain open. Duration at this location: 10 days.

2) Sanchez Street between 17th and 18th Streets for an 8 and 24-inch water transmission main installation. Duration at this location: 5 weeks.

Monday, March 30, 2009

Construction at Noe and Hill Streets

K. J. Woods Constructions Inc, the contractor working for the SFPUC, is waiting for DPT permits to commence work at Market and Sanchez Streets. In the interim, the crew is working at the intersection of Noe and Hill this week. Sections of sidewalks are closed. Parking on Noe between 22nd and 21st Streets and 100 feet of Hill at Noe Streets is restricted. Advance notice had been posted.

The contractor will proceed to Liberty between 21st and 20th Streets later this week.

Friday, March 20, 2009

Join San Francisco Water on Facebook and Twitter!

March 22nd is U.N. World Water Day and nobody in the world has better water than San Francisco. In celebration of our incredible tap water and U.N. World Water Day, the SFPUC is giving away stainless steel water bottles so you can bring our great tasting tap water with you wherever you go!

To get your own stainless steel bottle, join us on Facebook during the week of March 22nd-29th by becoming a FAN of San Francisco Water on Facebook at http://tinyurl.com/d3zxj5. (Log-in to your personal facebook account to view page).

The San Francisco Water Facebook page will be regularly updated with new photos, interesting videos, drought updates, water and energy conservation tips and more.

The first 1,000 San Francisco residents who become fans of San Francisco Water will be eligible to pick up a stainless steel water bottle after March 29. Pick up details will be announced on Facebook. Please help us spread the word by sending this to your friends and colleagues! Invite your network to join us on Facebook and Twitter.

Follow us on Twitter for more great SFPUC news. http://twitter.com/SFWater

Friday, March 6, 2009

Water Main Installation at Market and Sanchez

Construction will start the week of March 23, 2009 at the intersection of Market and Sanchez Streets. Parking on the West side of Sanchez (about 200 feet) will be restricted. Traffic delays can be expected, however at least one flag person will be onsite to direct traffic and ensure pedestrian safety.