Crew will be working at the intersection of Sanchez and Market streets this weekend, May 9 and May 10, and on Sanchez and 18th streets next weekend, May 16 and May 17 installing 8- and 24-inch water transmission mains. This weekend work is necessary because it’s the only time MUNI can take buses off-line so that construction work can proceed.
Construction crews will continue working at the following locations in the next few weeks:
19th Street between Sanchez and Noe. Duration: 3 weeks
Sanchez and Market Streets. Duration: 8 weeks
Tunneling and new water main installation will take place at the intersection of Sanchez and Market streets for 8 weeks.
Sidewalks will remain open, but PG&E and Comcast may need to close sections of the sidewalk at 17th and Sanchez streets and Market and Sanchez streets for utility work.