Excavation at the intersection of Sanchez and 17th streets postponed
Due to utility issue, crew will postpone excavation work at the intersection of Sanchez and 17th streets to late June. This work involves digging of large pits on both sides of the intersection and then pushing pipe through the pits. Duration: 8 weeks
The project team is making every effort to limit the “no parking” restrictions and monitoring the signs posted by the contractor closely. DPT has 72-hour advance posting requirement, so you may see “no parking signs” at blocks where no construction activity occurs. You are allowed to park prior to the start of construction or if no work has commenced by noon. In addition, the project team is looking for a staging area to store pipe and construction equipment to reduce the loss of parking spaces in these narrow corridors.
Our water operations crews are doubling their efforts to finish water pressure testing and make service connections to homes and businesses. They may even complete this work ahead of schedule.
Thank you for your patience and cooperation while we work to improve your drinking water delivery system. Please look for the June/July project update in the mail. For updates and comments please visit our blog: sfwater.org/district8.
Jim Chien, SFPUC Communications
415-554-3244
Friday, June 12, 2009
Wednesday, June 10, 2009
Why the Contractor needs NO PARKING signs
Restricted “no parking” signs located at 19th near Sanchez and on the side streets are for upcoming work to install the branch lines that will supply water to homes and businesses. While there is currently no activity, DPT requires that these signs be posted three days in advance. Today, the contractor took up some new “no parking” spaces as they have discovered a leak in the newly installed 8” pipeline and need to make the repairs.
To all concerned: Every effort is being made to limit the “no parking” restrictions as much as possible. If a staging area could be secured nearby for pipe and equipment, we certainly would do that.--Resident Engineer.
To all concerned: Every effort is being made to limit the “no parking” restrictions as much as possible. If a staging area could be secured nearby for pipe and equipment, we certainly would do that.--Resident Engineer.
Friday, May 29, 2009
Updates: Sanchez & 19th to Market & 15th

Crews will be working at 3 locations over the next week to accomplish water pipeline improvements. Our contractor will be installing new water mains while the City water operations crews will be making connections to residences and businesses.
We appreciate your patience and cooperation as work is performed in very tight corridors. We are working to minimize the parking we take out and to limit dust and debris as much as possible. Without closing down the streets entirely, this is a very demanding work for the crews in multiple locations.
Sanchez@ Market and 15th: Crew is digging under the MUNI tracks. This will require open pits on north and south side of Market Street. Northeast sidewalk will be closed while others will remain open with flagger for safety.
Sanchez between 16th and 18th: City water operations crews are making service connections and pressure testing. Sidewalks will remain open.
19th between Sanchez and Noe: No construction activity scheduled until the following week. However, construction equipment and pipe will remain while the crew prepares work. We have requested that the crews to remove all extraneous items at the end of the week.
Let us know how we can make this construction more neighbor-friendly. We appreciate your comments.
Thursday, May 21, 2009
Excavation begins at Sanchez & Market

Crew will begin excavation work at the intersection of Sanchez and Market streets early next week and Sanchez and 17th streets the following week installing new 8 and 24-inch water transmission mains. This work involves digging of large pits on both sides of the intersection and then pushing pipe through the pits. Duration: 8 weeks
Sidewalks will remain open, but PG&E may need to close sections of the sidewalk at 17th and Sanchez streets and Market and Sanchez streets for utility work.
Construction crews will continue working at the following locations in the next few weeks:
19th Street between Sanchez and Noe. Duration: 3 weeks
Sanchez between 16th to 18th streets: Duration: 4 weeks
We might need to come back to the same streets to continue work. We appreciate your patience as we work to improve your drinking water delivery system. For updates and comments on the project, please visit: sfwater.org/district8
Friday, May 8, 2009
Weekend work at the intersection of Sanchez and Market streets; Sanchez and 18th streets
Crew will be working at the intersection of Sanchez and Market streets this weekend, May 9 and May 10, and on Sanchez and 18th streets next weekend, May 16 and May 17 installing 8- and 24-inch water transmission mains. This weekend work is necessary because it’s the only time MUNI can take buses off-line so that construction work can proceed.
Construction crews will continue working at the following locations in the next few weeks:
19th Street between Sanchez and Noe. Duration: 3 weeks
Sanchez and Market Streets. Duration: 8 weeks
Tunneling and new water main installation will take place at the intersection of Sanchez and Market streets for 8 weeks.
Sidewalks will remain open, but PG&E and Comcast may need to close sections of the sidewalk at 17th and Sanchez streets and Market and Sanchez streets for utility work.
Construction crews will continue working at the following locations in the next few weeks:
19th Street between Sanchez and Noe. Duration: 3 weeks
Sanchez and Market Streets. Duration: 8 weeks
Tunneling and new water main installation will take place at the intersection of Sanchez and Market streets for 8 weeks.
Sidewalks will remain open, but PG&E and Comcast may need to close sections of the sidewalk at 17th and Sanchez streets and Market and Sanchez streets for utility work.
Thursday, April 16, 2009
Construction Updates # 5

Construction crews will be working at the following locations installing an 8 and 24-inch water transmission main late this week or early next week:
Noe Street between 19th and 20th. Duration: 7 days
19th Street between Sanchez and Noe. Duration: 10 days
Intersection of Sanchez and 18th Streets. Duration: 3 days.
Sanchez between 17th and 18th Streets. Duration: 7 days
Sanchez between 16th and 17th Streets. Duration: 10 days.
Traffic: One-lane traffic will be maintained. Flag persons will be on site to direct traffic. Work Hours: 8:00 am – 5:00 pm.
Parking: Restricted parking signs have been posted. If no construction takes place by noon, public parking is permitted. The areas currently used to lay down transmission pipes will be occupied for approximately 5 weeks.
Sidewalks will remain open, but PG &E may need to close sections of the sidewalk at 17th and Sanchez Streets for utility work.
We appreciate your patience as work to improve your drinking water delivery system.
Wednesday, April 8, 2009
Construction at Noe btw 20th & Liberty and Sanchez btw 17th & 18th
Crew currently working at Noe Street between 22nd and 21th Streets will proceed to the following locations later this week:
1) Noe Street between 20th and Liberty Streets for a 24-inch water transmission main installation. Sidewalks will remain open. Duration at this location: 10 days.
2) Sanchez Street between 17th and 18th Streets for an 8 and 24-inch water transmission main installation. Duration at this location: 5 weeks.
1) Noe Street between 20th and Liberty Streets for a 24-inch water transmission main installation. Sidewalks will remain open. Duration at this location: 10 days.
2) Sanchez Street between 17th and 18th Streets for an 8 and 24-inch water transmission main installation. Duration at this location: 5 weeks.